On Monday, February 1, 2021, Jet Jack Contracting will begin work on Angerer Road to construct a pipe culvert. Once constructed, the pipe culvert will be backfilled with foreign borrow soil to buttress and stabilize the roadway embankment. Work includes clearing and grubbing, installation of RCC pipe, concrete headwall, and end wall, placement of rock lining, and installation of a temporary rock construction entrance, and roadway pavement reconstruction within the limits of the work.

Angerer Road will remain open to thru traffic during construction, a flag person will direct traffic when construction vehicles are entering or leaving the worksite. The motoring public may encounter intermittent, short delays.